
Set the truck outside the north entrance on the drawing. The belt route winds past two columns to the final bay, while the plant aisle has to remain usable. That is already enough information to rule out several long, one-piece frames. Check the supports and guarded width on the route before specifying the belt itself.
01 Two Concrete Duties, Two Enquiries
The word concrete appears on two quite different enquiries. One asks for a belt carrying aggregate around a yard. The other asks for fresh mix inside a building, with people finishing a slab as the belt runs. The latter brings paste leakage, access, cleaning and interruption into the design.
For an indoor slab, the doorway and the placing front may determine the equipment before capacity does. A wide machine that cannot clear a column is not useful, however impressive its catalogue rate.
Two duties, one invoice, two completely different answers
An outdoor line has room to spread out. Indoors, the receiving hopper might sit outside while the first frame section has to turn immediately after the door. Send the conveyor belt manufacturer that turn as a dimensioned plan. A photograph taken straight through the doorway will conceal it.
Draw the discharge height at each bay. The belt may fit through the door while the support legs or head pulley do not.
The four constraints that make an indoor pour different
There is a cable tray beside the entrance, below the level shown for the conveyor head. Measure beneath it. Mark the traffic aisle on the same sheet, because a frame can fit through the door and still leave the plant unable to operate during the pour.
Field check: Measure the turn inside the 2.4 m entrance with the full guarded section, drive and legs in the outline.
The product catalogue gives belt and component dimensions. One number to check against the doorway is overall guarded frame width, not only the nominal belt width. A drive mounted outside the side frame can be the part that catches the door jamb.
02 Draw the Route from Truck to Wash-Out
A conveyor that keeps running into a blocked discharge creates a problem at the very point where the floor finish matters most.
The six zones of a floor pour
The table starts with a truck and ends with dirty wash water. Between them are four ownership questions. Who releases the hopper? Who calls for a stop at the head? Who moves the end chute? Who accepts the next bay? Name those people during the pre-pour walk.
| Zone | Crew action | Equipment interface | Watch at handover |
|---|---|---|---|
| Truck stand | Deliver approved mix | Hopper or feeder | Queue and safe access |
| Feeder | Meter the stream | Truck to belt | No surge or segregation |
| Conveyor run | Carry to bay | Supports and guards | Clearance and tracking |
| Discharge | Place the strip | Chute to crew | Controllable flow |
| Finish | Consolidate and level | Crew to next bay | Pause upstream feed |
| Wash-out | Remove paste | Water and solids collection | Return and joint clean |
Where the conveyor physically sits on the plan
For every bay in the pour sequence, add the proposed positions of the frame feet. Now repeat the exercise for the power lead and movable discharge. A support shown on newly placed concrete calls for an engineered temporary arrangement or a different sequence.
A straight elevation is a poor access test for this room. The section has to turn around a column directly after the doorway. Mark the swept outline of the drive, guards and legs at that corner; the narrowest clearance belongs on the supplier's installation drawing.
Send the conveyor belt supplier a route sketch with the enquiry. At each transfer, mark the point of discharge and the space left for cleaning. The industrial conveyor belt quotation can then identify a cover and joint for those particular contact points.
03 What the Mix Does at the Loading Point
Slump is a property of the specified mix, not a number to alter merely to suit the machine. Before choosing a belt or pump, look at the approved mix design and the actual route. A very fluid mix may be difficult to retain on an inclined belt; a stiff mix can bring other placement problems. The project's concrete specialist decides what may change.
Reading slump before you choose between a belt and a pump
A short, accessible run with a mix that holds its shape may suit a belt. A long lift, a convoluted route or a mix designed for pumping may favor a pump. There is no universal slump boundary that makes the decision for every chute and belt angle. Trial the proposed mix at the intended loading and discharge points.
Adding water at the truck to make a belt easier to use is a poor procurement solution. It changes the approved mix.
Aggregate top size, cover hardness and the puncture risk
The largest aggregate is a loading-point question as well as a cover question. Angular stone falling onto an unsupported belt can cut a rubber conveyor belt even if the broad face resists abrasion well. Record top size, drop height and impact support. A small drawing of the chute exit is often more useful than the word 'coarse.'
Specify the cover by tested properties and the loading arrangement, rather than ordering a hardness number alone. A hard cover can still be punctured by one awkward stone.
The difference may reflect travel, handling or waiting. Do not assume the mix at the placing front behaves exactly as it did at the drum; check what the crew actually receives.
04 Specify the Belt for Placement
Fresh concrete leaves paste wherever it can escape. Its aggregate loads the cover in points, and the crew expects the belt to wash clean before the next use. Those are the three things I would put beside the proposed carcass and splice on a belt order.
Alkali, abrasion and tear: the three cover demands
Wet paste reaches the face, skirt and cut edge during each load. For the cover, request the supplier's relevant compatibility and adhesion results under the proposed cleaning cycle. A dry abrasion sheet alone says nothing about the joint that remains wet overnight.
The rubber conveyor belt cover grades guide is useful for comparing test properties, but the chute and support must be examined too. Extra cover thickness will not remove a trapped piece of aggregate.
Cleanability, splice strength and a leak-proof skirt interface
Paste remains in a deeply textured sample after a quick wash. Test a smoother face with the approved mix too, watching for rollback on the incline. Keep the washed samples for inspection rather than judging the clean catalogue pieces.
Show the proposed joint in section. The conveyor belt splicing methods available for this carcass differ at the surface: one may leave a step near the cleaner, another may take more belt length and field time. Inspect the selected joint after passing real mix and wash water through the machine.
| Belt item | State on order | Evidence to request | Field concern |
|---|---|---|---|
| Cover | Compound and thickness | Test data for duty | Paste, wear and cleaning |
| Carcass | Tension and ply build | Construction sheet | Impact and bending |
| Splice | Method and dimensions | Joint drawing and procedure | Leak and cleaner contact |
| Edge | Seal and width | Cross-section detail | Paste ingress and rubbing |
| Length | Installed loop allowance | Take-up drawing | Enough travel after splice |
| Surface | Finish and cleaning method | Trial observation | Paste release and grip |
Length must cover the installed path, splice allowance and take-up travel. The drawing should state the measured loop length and how much adjustment is available after splicing. A spare cut exactly to the nominal route can be short when the crew finally fits the joint.
The conveyor belt factory quote covers a loop. On the buying sheet there is also the support frame, installation, cleaning water and a spare joint. A line from the wholesale conveyor belts list may be cheap per metre and expensive if it cannot be spliced and cleaned within the pour schedule.

05 Machine Combinations and Handoffs
At a trial discharge, the placing crew calls for a pause. Does the feeder stop before material piles up at the head? Where does the mix already on the belt go? That short exchange tests the interface between machines more usefully than each motor's separate nameplate rating.
Mobile, incline and telescopic configurations
A radial conveyor can cover an open area; an incline may clear formwork; a telescopic discharge can reach without repeated frame moves. None is a default for every room. The turning radius and support positions on the plan decide which combination the crew can actually use.
| Configuration | Useful where | Check before pricing | Interface at discharge |
|---|---|---|---|
| Mobile radial | Open room with sweep space | Support and turning path | Controlled end chute |
| Incline section | Over a local obstruction | Rollback and headroom | Feed and receiving height |
| Telescopic end | Reach changes with bay | Extension and support | Stable placement point |
| Modular frame | Narrow access | Section size and lifting | Joint alignment |
| Fixed line | Repeated straight pour | Traffic conflict | Reach of placing crew |

Drive, control and the parts nobody puts on the drawing
Speed control helps the placing crew match the flow to the front. Check the drive's starting condition with a loaded belt and the intended stop sequence. The operator needs a clear way to pause upstream feed before the discharge becomes crowded.
Paste on the return can reach bearings and build on roll shells. Show the conveyor roller range and cleaner positions on the layout, with access for washing. A sealed bearing is useful, but it does not make a roll buried in set mortar maintainable.
The conveyor belt distributor may stock the loop but not the modular frame. Put separate lead times against them. The transmission belt manufacturer spare belongs under the drive, not under the carrying-belt dimensions; the crew will need to know which box to open if the machine stops.
06 Check Volume, Mass and Belt Capacity
Capacity is a pair of calculations. First find the fresh mix volume and the placing rate needed in the available window. Then check whether the proposed belt's usable cross-section and speed can carry that volume. A catalogue tonnage by itself does not settle either question.
The two-step capacity calculation
The calculation has two lines on the worksheet. Volume to mass: 60 m³/h × the assumed fresh density of 2.4 t/m³ = 144 t/h. Belt flow: 3,600 × the loaded area of mix in m² × speed in m/s = m³/h. The first density is replaced by the approved mix figure. The loaded area needs a supplier drawing or trial; belt width alone cannot supply it.
A Worked Volume Takeoff
Takeoff note beside the sketch: slab 192 m³ (48 × 20 × 0.20 m); separate plinth allowance 11.52 m³ (eight at 1.2 × 1.2 × 1.0 m). The two add to 203.52 m³, subject to a check for overlap. If 205 m³ is ordered and actual flow is 60 m³/h, the belt runs for about 3.42 hours before stops. Put the truck and wash time elsewhere on the programme.
Try the wider option against the doorway drawing. Its guards may foul the jamb even though it could carry the same flow at a gentler speed. The supplier's actual loaded section of concrete, the available space and the discharge shape all have to work together.
Pour window and continuous supply check
The six-hour access permit is not six hours of belt flow. In the example schedule, two hours are allocated to setup and other work. The remaining four call for roughly 51 m³/h at the placing front. Lay the truck dispatch slots alongside the belt's proposed 60 m³/h output to see whether that rate can be sustained.
Field check: The truck schedule governs the hopper feed. Compare its delivered volume by hour with the rate used in the takeoff.
07 Protect the Placing Front
Where a cold joint actually forms
The placing arrow on the plan doubles back beside a strip laid earlier. How long has that strip been waiting? Write the return time next to the arrow. The engineer can then judge the mix and temperature against the proposed sequence, or draw a construction joint where one is intended.
A two-minute pause while the crew moves a chute is one thing. A missing truck is another. The foreman needs a clear point at which the next bay is held and the concrete engineer is called. That decision should be in the briefing before the feed is switched on.
The site's other drives also need attention before pour day. If an essential fan or mixer depends on a V-belt manufacturer spare, put that spare beside the concrete equipment list. The point is continuity of the work, not a claim that every drive belt is part of the placement conveyor.
08 Trouble Seen During a Trial Pour
Most expensive floor-pour faults start small: paste below a skirt, a stone riding the belt, an aisle blocked at the wrong time. Each may be visible during a short trial with actual mix.
The Wet Line Beneath a Skirt
Wet mortar appears beneath the left skirt while the line is loaded. The seal was close to the empty belt, but the carrying strand sags at the hopper. Check support and loaded tracking; the belt tracking guide can help locate a sideways drift, but tightening the skirt until it cuts the cover is no fix.
At the feed point, a stone can strike the cover and remain lodged in paste. When the belt returns, it may score a roll or cleaner. After the trial, inspect both faces and the first return rolls. If damage is concentrated under the drop, change the impact and chute arrangement before buying more cover.
Wash-down between pours
The belt cleaning methods assume somebody can reach the return. On the plan, that side runs close to a wall. Move the wash point or provide access before the first load, and show where the water and cement solids will be collected.
Field check: A Friday wash missed the underside in this hypothetical inspection. By Monday the remaining paste is hard against the return rolls; show how the crew can reach that side.
09 When Can the Aisle Reopen?
Do not reopen the aisle because the floor has become walkable. Vehicle wheel loads need a different check. The engineer of record sets the strength evidence for that slab; until it is accepted, use the old route or a properly supported temporary crossing.
How long before a forklift can cross the slab
A forklift date written on the programme is a target, not proof of strength. The project engineer must relate the actual vehicle and wheel loads to the slab design, curing and test evidence. Until that approval, the traffic route stays off the new bay, however dry the surface appears.
10 Mistakes to Catch on the Drawing
Four Red Marks on the Draft Plan
Four pencil marks on the plan are enough to return the draft: the guarded frame's turn at the door, the last bay beyond the chute, the hourly truck arrivals, and the slurry destination. The supplier can answer those items on a revised drawing.

Sections may get around the column where an assembled frame will not. The lifting points and the means of aligning the joints still need a drawing. Do not price a modular route from a claim that two workers can carry it.
11 What the Enquiry Must Show
Send the annotated floor plan, mix sheet and truck slots as one enquiry pack. Request a matching supplier drawing with the section lengths, feet and transfer points marked. That drawing is the item the crew can check at the site gate.
What to put in the enquiry
| Enquiry item | Buyer supplies | Supplier returns |
|---|---|---|
| Room plan | Doors, columns, traffic | Equipment footprint |
| For | Volume, window, sequence | Rate and operating plan |
| Mix | Approved properties and top size | Trial and belt proposal |
| Conveyor | Run, lift, discharge | Layout and capacity basis |
| Utilities | Power and wash-water route | Drive and cleaning drawings |
| Saved | Expected reuse and stops | Belt and joint identification |
Acceptance tests at handover
| Handover check | Method | Agreed evidence |
|---|---|---|
| Access | Move sections along route | Measured clearances |
| No-load run | Track and stop sequence | Observed stability |
| Loaded trial | Approved mix at rate | Flow and discharge record |
| Skirt and return | Watch for paste loss | No unacceptable leak |
| Wash-out | Clean full circuit | Accessible and complete |
| Records | Compare with order | Drawings and test sheets |
At handover, an empty tracking run is only the beginning. The loaded trial should show where mix lands, what reaches the placing front and whether paste escapes beneath the skirts. Record the result before the first full pour.
12 Where This Guide Fits
Our other concrete page treats movement around an outdoor works area. Here the truck remains outside a building and the discharge has to follow a floor pour past columns and live traffic. That room plan is what changes the equipment discussion.
The aggregate abrasion guide deals with cover wear under a bulk load. Here the mix itself, the moving placing front and the wash-down sequence decide whether that cover works. Use the earlier page for a material discussion and this one for the floor route and procurement checks.
13 Keep the Evidence with the Machine
The project concrete specification governs mix and strength acceptance; belt tests and machine safety documents answer other questions. Do not substitute one certificate for all three.
Keep the shipment file practical: belt construction and cover test values, splice drawing, installed length and take-up range, drive and guard drawings, and the loaded trial record. A missing splice detail becomes a serious problem when a field crew has to repair the loop during a pour.
14 Questions Before the Pour
Will a standard rubber belt work here?
A rubber loop may fit this service, but the name of its material tells little about the assembled machine. Look at its cover with the proposed mix, the cleaner's contact at the splice and the result after washing. Record both loss of paste and retained material during the loaded trial.
What belt speed makes sense for placing concrete inside a building?
Start with the placing rate and the loaded cross-section that the proposed frame can carry without loss. The speed follows those numbers, then the operator tests whether discharge can be slowed for the crew. A brochure speed copied onto every indoor floor plan is not useful.
Would a pump reach the bay more easily?
There is a wall between the truck and the work. A pump pipe can go overhead, but its outlet and wash point still need space. A belt route is possible if the door and column turn leave enough room for the frame. Check both against the same pour sequence and mix sheet.
How do we stop mortar leaking out under the skirt board?
The belt may lie under the skirt when empty and dip away under a hopper load. Watch that loaded gap in the trial. Tightening the rubber until it scrubs the cover replaces a paste leak with a wear groove; the support and tracking need attention too.
What happens at a mechanical joint?
The raised joint on the sample holds paste around its fasteners. That may be unacceptable on this line, particularly at the cleaner. Ask for a loaded leak test if a mechanical joint is proposed. A vulcanised alternative needs its own drawing, length allowance and field procedure.
Which slump can this route carry?
Ask what happens with the approved mix on the proposed incline. Does paste run beneath the skirt? Does aggregate roll back or separate at discharge? Those observations, together with the mix designer's limits, answer the question for this conveyor. There is no safe universal slump number to print on the order.
How does coarse aggregate damage a placement belt?
Below the chute is a shallow bruise with a small angular stone still pressed into it. That single mark points to the drop and belt support. Remove the stone, inspect the return path for scores and change the landing arrangement before assuming another cover grade would survive.
What evidence opens the forklift route?
The forklift route reopens only after the engineer accepts evidence of adequate in-place strength for that vehicle and slab. A date on the programme cannot stand in for the check. Draw an alternative crossing before the pour if production cannot wait.
Is washing required after a pour?
Yes. Allow for washing while cement paste is still soft. At the trial, time the full circuit: return rolls, joint, skirt pockets and the collecting point for slurry. The inspection should include the underside, which a clean photograph of the carrying face will not show.
Related Products You May Need
- Rubber conveyor belt — select its cover and splice from the actual mix trial.
- EP fabric conveyor belt — check tension and the smallest pulley on the modular route.
- Conveyor rollers and idlers — place access for the return side on the layout.
- Chevron and cleated belt — trial grip and cleaning before selecting an incline profile.
- V-belts for plant drives — identify the spares by the drive they fit.
- Full product catalog — use dimensions alongside the guarded frame drawing.
Related Blog Posts
- Rubber belt cover grades explained — compare the cover tests with the old belt sample.
- Conveyor belt splicing guide — show the field joint on the installation drawing.
- Belt cleaning methods and schedules — put wash-out access into the floor plan.
- Belt tracking field guide — check a loaded belt before adjusting the skirt.
- Return side belt cleaning — inspect the side the crew cannot see from the control.
- Abrasion-resistant belts for aggregate — distinguish stone impact from steady surface loss.
- Splicing buyer's checklist — record joint length and take-up travel.
- Dust-resistant belt supply — consider the material stream and the impact point.
- Heavy-duty rubber belts in mining — inspect the relevant construction drawings.
- Inside our conveyor belt factory — verify manufacturing data against the duty.









